In Krasnoyarsk, they plan to strengthen the sliding slope in the area of 2nd Ogorodnaya and Dachnaya streets. The city administration has provided 1.9 billion rubles for these purposes. In the first quarter of 2025, tenders will be held to find a contractor who will carry out engineering and survey work.
In addition, next year the Krasnoyarsk authorities intend to concrete sections of water wells near the problematic building. This will be handled by the contractor who built the storm drain. The work will be carried out under warranty.
Photo: ru.freepik.com
The storm sewer system is 97% ready. At this stage, the shortcomings identified by the regional Construction supervision are being eliminated. The storm drain will be put into operation next year.
Problems with the sliding slope in the area of 2nd Ogorodnaya Street have been observed since 2020. In 2015, construction of apartment building No. 22a began there. It was put into operation in 2017, and in 2020, after heavy rains, part of the slope collapsed next to the building.
To solve the problem, it is necessary not only to strengthen the slope, but also to build a storm drain to drain water. The storm drain began to be built in 2022, Krasnoyarsk Online reports.
It should be recalled that investments in the economy of the Krasnoyarsk Territory have reached a record amount.