More than 900 workers are involved in the construction of the second stage of the UrFU campus in Yekaterinburg

188
1
More than 900 workers are involved in the construction of the second stage of the UrFU campus in Yekaterinburg
August 8th. /MEDIA TALK/.The buildings are planned to be commissioned at the end of 2025.

In Yekaterinburg, the construction of academic buildings of the second stage of the UrFU campus in Novokoltsovsky district is actively underway. The work is carried out by the Sinara Development company.


Photo: ru.freepik.com

At the moment, builders are erecting buildings of the Institute of Radioelectronics and Information Technology, the Institute of Economics and Management and a Specialized educational and Scientific Center. The area of the buildings is 100,000 square meters.

In IRIT-RTF, monolithic structures of three floors are almost 100% ready, builders are erecting external and internal walls, insulating the facade and making roofs.

INEU has almost completely flooded the first floor of the three, the second is ready for more than a third. Walls and partitions are also being erected, workers are installing pipes, sewers, heating system, ventilation and smoke extraction system.

In the SUNCA building, builders are erecting the fourth floor, assembling partitions, and roughing the basement. The process of facade insulation, installation of translucent structures has also begun, roofing works are underway.

The campus is an important project for scientific and technological development and attracting talented young people to the region. More than 8000 students will be able to study at the university, TASS reports.