According to Deputy Governor Evgenia Mazanova, the roof and facade of the facility were repaired, the interior was finished, metal structures were installed and pumping equipment was replaced. This made it possible to ensure reliable drainage of wastewater into the sewer system and further develop the drainage system in the neighborhood.
Photo: ru.freepik.com
The modernization was carried out in 2 stages. First, the specialists updated the existing sewage pumping station. The work cost 60 million rubles. At the second stage, a pressure collector with a length of almost 6 kilometers was built for 218 million rubles.
The new pipeline was connected to the pumping station and put into operation. The reconstruction of the facility will allow connecting new subscribers to the wastewater disposal system, the press service of the Vologda Oblast Government said.